Column About Transitioning to Agile in the Middle of a Project

My Stickyminds column, Transitioning to Agile in the Middle of a Project, is up. Enjoy!

2 Comments so far
Leave a comment

Hi Johanna,

I’m interested if the story you tell in the article is a true one (with names changed), or if its “made up” but based on experience.

In particular is the “25 hours verses 5 hours” real or hypothetical data?

Cheers
Mat

Mat, yes, the data happens to be real. The names are changed.

It really was a 5 hour dev investment to prevent 25 (to 30) hours of post dev finding and fixing.