Using Multiple Life Cycles in Combination on a Project, Part 3
I’ve also used Agile life cycles (Scrum with different size timeboxes) in combination on a project.
Here, the developers in the corporate location had a series of features that were big. I did suggest they break the features apart into smaller chunks for ease of estimation and implementation, but they didn’t want to
The remote team was responsible for smaller chunks of features, and were having trouble estimating the size of their stories. They decided to move to 2-week timeboxes to reduce what they were trying to estimate.